Concrete Machinery: Pumps, Mixers, Plants
Three different machines in one chain: the plant produces concrete, the mixer takes it to the site, the pump feeds it into the mold. A selection error in one of the links — the concrete is waiting on the site and begins to set. We select the system taking into account peak productivity, transportation distance, delivery height and concrete class.

Types & Configurations
Each type is a separate range of parameters and its own task. A wrong choice here leads to overspending or downtime.
Parameters Without Which Selection Does Not Start
| Boom departure (concrete pump) | m, horizontally and vertically. Determines whether to reach working points. |
| Pump performance | m³/h at maximum and working pressure. Agrees with the plant and the volume of the receiving form. |
| Volume of the mixer drum | m³, taking into account the filling of 80-85%. The standard is 9 m³ for most objects. |
| Class of concrete | Brand, mobility, crushed stone fraction. Affects supply pressure and wear of hydraulic components. |
| Chassis type | 6×4, 8×4, 10×4. Depends on the permissible axle load in the region. |
Typical Applications
What is Actually Ordered in Ukraine
FAQ
What boom is needed for a building up to 16 floors?
As a rule, 42-46 m, taking into account 3 m for the height of the crane installation and the distance from the unloading point. If the car will stand further (due to the narrowness of the site) — take 52 m.
How many mixers are needed for one auto pump?
Depends on the cycle. If the plant in 20 minutes and the pump supplies 50 m³/h - 3-4 mixers of 9 m³ in continuous logistics. For distant objects — 5-6.
Will you put in a turnkey concrete plant?
Yes. Stationary 60-120 m³/h with silos, dispensers, control, foundations and commissioning. European, Turkish and Chinese manufacturers with a complete project.
What is the resource of a concrete pump?
Pistons and hydraulic cylinders — 50-80 thousand m³ before replacement. Concrete mixing drum — 5-7 years. With proper maintenance, the machine works for 15-20 years.
Inputs for an accurate equipment selection
Start with these details. Mark any unknown requirement in your enquiry so it can be clarified before a model is selected.